Winning bids · Part 3 of 3
Buffers ate your price.
You rarely lose on your competitor's estimate. You lose on buffers nobody wrote down, added once more at every review.
When a bid is lost on price, the usual conclusion is that the competitor was cheaper or estimated more aggressively. In my experience that is rarely what happened. You rarely lose on your competitor's estimate. You lose on your own buffers.
How a fair price turns into a high one
Follow one estimate through a typical bid. The numbers below are an illustration, but the pattern will be familiar.
- The estimator adds 20% because some requirements are unclear.
- The technical lead adds 15% because the technology is new to the team.
- The reviewer adds 10% because this is a new customer.
- Commercial adds 10% contingency on top.
Each step looks reasonable on its own. Together they compound: 1.20 × 1.15 × 1.10 × 1.10 is about 1.67. The price is now two-thirds higher than the estimate the team actually believes, and nobody decided that it should be.
Worse, most of these buffers are never written down. They live in the head of whoever added them. By the time the price is approved, nobody can say which part of it is the work and which part is fear.
Why everyone pads
There is no industry standard for how fast a team builds on a given technology, in a given domain. No company shares its real figures with anyone, and published ones are of little use. So every estimator is guessing, and a careful person protects themselves. Every review stage does the same, because nobody wants to be the one who approved the estimate that went wrong.
The result is a price that tells the customer one of two things: that you do not understand their work, or that you do not trust your own team. Either way, trust takes the hit. And a vendor who comes in far above the rest is often not invited to the next bid either.
What to do instead
1. Calibrate your own baseline
You cannot borrow anyone else's figures, so make your own. Write a small reference specification, a handful of screens with a mix of fields and validations, some of them complex, in a page or two. Give it to six people of different experience, in two groups of three, on the same day, with no chance to confer. Ask each for hours to build and unit test it, and to write the test cases. The average and the spread are your baseline, and the spread tells you how much uncertainty is real. Compare it with estimate-versus-actual figures from a finished project to see how much rework to expect. Do it once and reuse it across bids.
2. Turn every buffer into a written assumption
"Plus 20% for unclear requirements" becomes "requirements 4.2 to 4.9 are unclear; we assumed X; if it is Y the effort grows by this much." Now a reviewer can challenge the assumption instead of adding another buffer, and the customer can see exactly what would change the price.
3. Get two independent estimates on large bids
On a bid that matters, have two teams estimate separately from the same brief. Where they agree, you can be confident. Where they differ, you have found the real risk, and you can deal with it directly instead of padding everything.
4. Set the price band before anyone designs the answer
If the customer has given a budget, or sales has heard one, compare your rough estimate with it early, before the detailed work starts. If you are far above it, look at the levers: which parts of the scope are critical, essential or merely desirable, phasing, the mix of the team. Then decide, on purpose, whether to bid, bid a smaller scope, or walk away. Discovering the gap at the end, after the customer has formed a view, is too late.
5. Be honest about what you cannot price
Sometimes one requirement cannot be estimated with confidence: a technology nobody on the team has used, or a third party whose plans are uncertain. Don't hide a guess in the total. Say plainly that it cannot be priced yet, show the alternatives, and offer a short, separately priced stage, such as a proof of concept, whose result fixes the main price. Customers trust that kind of honesty far more than a padded number.
6. Show the price so it can be understood
Show the price per phase, and per scope class if budget is tight, so the customer can choose what to buy. List the factors that could move it and which way. A price the customer understands is a price they can defend inside their own company.
A tight price is a message
A clear, explained price tells the customer something no slide can: we understand your work, and we trust our own estimates. That is a trust signal, and it often matters more than the last few percent.
The method behind it: 37% won on competitive bids to new customers, 2008–2013, with undecided bids counted as lost.
Optimium runs every bid with a calibrated baseline, written assumptions and a price band set before the detailed work starts, so the number you submit is one you can explain.